Posts Tagged ‘product development’

The Goldilocks Dilemma

November 26, 2014 Leave a comment

With increasing product complexity comes the necessity for technical specialization. For example, I help build multi-million dollar air defense and air traffic control radars that require the integration of:

  • RF microwave antenna design skills,
  • electro-mechanical design skills,
  • physical materials design skills,
  • analog RF/IF transmitter and receiver design skills,
  • digital signal processing hardware design skills,
  • secure internet design skills,
  • mathematical radar waveform and tracker design skills,
  • real-time embedded software design skills,
  • web/GUI software design skills,
  • database design skills.

Unless you’re incredibly lucky enough to be blessed with a team of Einsteins, it’s impractical, to the point of insanity, to expect people to become proficient across more than one (perhaps two is doable, but rare) of these deep, time-consuming-to-acquire, engineering skill sets.

As the figure below illustrates, one of the biggest challenges in complex product development is the Goldilocks dilemma: deciding how much specialism is “just right” for your product development team.

Just Right

Too much specialism leads to an exponential increase in the number of inter-specialist communication links/languages to manage effectively. Too little specialism leads to the aforementioned “team of Einsteins” syndrome or, in the worst case, the “too many eggs in one basket” risk.

So, is there some magic, plug & play formula that you can crank through to determine the optimal level of specialism required in your product development team? I suspect not, but hey, if you develop one from first principles, lemme know and we’ll start a new consulting LLP to milk that puppy. Hell, even if you pull one out of your ass that people with lots o’ money will buy into, still gimme a call.

Abstract Decomposition And Concrete Composition

November 6, 2014 1 comment

On the left we have the process of abstract decomposition, and on the right we have the process of concrete composition:

Decompose And Compose

Note that during the concrete composition from parts to final system on the right, we gracefully transition through two stable, intermediate forms. Some people and communities, especially those obsessed with “velocity” and “time-to-market“, would say “bollocks” to all those value-subtracting, intermediate steps. We no need no stinking intermediate  forms:

direct composition

 

 

 

 

The Trees And The Forest

November 3, 2014 Leave a comment

As a result of an online Twitter exchange with Mr. Jon Quigley, I was able to purchase a copy of his and Kim Pries’s book, “Project Management Of Complex And Embedded Systems“. In exchange for a half-price deal, I promised to blog a review of the book and, thus, this is it.

quigley book

As indicated by the book title, the subject matter is all about the methods and tools commonly used by program/project managers for orchestrating large, capital-intensive, multi-disciplined, product development endeavors. Specifically, the content focuses on how the automotive industry successfully manages the development and production of products composed of thousands of electro-mechanical parts and hundreds of networked processors, some of which run safety-critical software. Even though we tend to take them for granted, when you think about it, an automobile is an extremely complex distributed system requiring lots of coordinated mental, physical, and automated, labor to produce.

The book provides comprehensive, yet introductory, coverage of the myriad of tools and processes used in the world of big project management. It’s more of a broad, sweeping, reference book than a detailed step-by-step prescription for executing a specific set of processes. It’s jam packed with lots of useful lists, figures, tables, and graphs. The end of each chapter even includes a specific “war story” experienced by one or both of the authors over their long careers.

As a long time software developer of complex embedded systems in the aerospace and defense industry, much of the book’s subject matter is familiar to me. RFPs, SOWs, WBSs, EVM, BOMs, V&V, SRRs, PDRs, CDRs, TRRs, FMEA, staged-gate phases, prime-subcontractor relationships, master schedules, multi-level approvals, quality metrics, docu-centric information exchanges, etc, are amongst the methods used to facilitate, focus, constrain, and guide end-to-end system development. Many of the chapter-ending war stories tickled my funny bone too!

For the types of projects Mssrs. Pries and Quigley target in the book, kicking off a project at sprint 0 with a self-organizing team of eight cross-functional developers and a primed product backlog of user stories just doesn’t cut it. So, if you’re a young, naive, cloistered software developer or scrum master or product owner who belittles all “traditional“, rigorous, non-agile processes, I highly recommend this book. It will give you a glimpse into a whole different world and broaden your horizons – perhaps allowing you to see both the trees and the forest.

A Skeptical “No”

May 5, 2014 7 comments

Just about every agile video, book, and article I’ve ever consumed assumes some variant of the underlying team model shown below. The product these types of teams build is comprised of custom software running on off-the-shelf server hardware. Even though it’s not shown, they also assume a client-server structure, request-response protocol, database-centric system.

SW only

The team model for the types of systems I work on is given below. They are distributed real-time event systems comprised of embedded, heterogeneous, peer processors glued together via a pub-sub protocol. By necessity, specialized, multi-disciplinary teams are required to develop this category of systems. Also, by necessity, the content of the sprint backlog is more complex and intricately subtler than the typical agile IT product backlog of “features” and “user stories“.

SW and HW

When I watch/read/listen to smug agile process experts and coaches expound the virtues of their favorite methodology using narrow, anecdotal, personal stories from the database-centric IT world, I continuously ask myself “can this apply to the type of products I help build?“. Often, the answer is a skeptical “no“. Not always, but often.

Where To Start?

April 6, 2014 4 comments

The purpose of abstraction is not to be vague, but to create a new semantic level in which one can be absolutely precise. — Edsger Dijkstra

With Edsger’s delicious quote in mind, let’s explore seven levels of abstraction that can be used to reason about big, distributed, systems:

seven-levels

At level zero, we have the finest grained, most concrete unit of design, a single puny line of “source code“. At level seven, we have the coarsest grained, most abstract unit of design, the mysterious and scary “system” level. A line of code is simple to reason about, but a “system” is not. Just when you think you understand what a system does, BAM! It exhibits some weird, perhaps dangerous, behavior that is counter-intuitive and totally unexpected – especially when humans are the key processing “nodes” in the beast.

Here are some questions to ponder regarding the seven level stack: Given that you’re hired to build a big, distributed system, at what level would you start your development effort? Would you start immediately coding up classes using the much revered TDD “best practice” and let all the upper levels of abstraction serendipitously “emerge”? Relatively speaking, how much time “up front” should you spend specifying, designing, recording, communicating the structures and behaviors of the top 3 levels of the stack? Again, relatively speaking, how much time should be allocated to the unit, integration, functional, and system levels of testing?

Formal Waterfall Events

March 31, 2014 2 comments

The customers of all the big government-financed sensor system programs I’ve ever worked on have required the aforementioned, waterfall, dog-and-pony shows as part of their well-entrenched acquisition process. Even prior to commencing a waterfall death march, as part of the pre-win bidding process, customers also (still) require contractors to provide detailed schedule and cost commitments in their proposal submissions – right down to the CSCI level of granularity.

If you think it’s tough to get your internal executive customers to wholeheartedly embrace an “agile adoption” or “no estimates” initiative, try to wrap your mind around the cosmic difficulty of doing the same to a large, fragmented, distributed authority, external acquisition machine whose cogs are fine-tuned to: cover their ass, defend their turf, and doggedly fight to keep the extant process that justifies their worth in place. Good luck with that.

Go Agile

Trivial Trivia

March 26, 2014 Leave a comment

I was going through some old project stuff and stumbled upon the chart below. I developed it back when I was the software lead of a nine person sub-team on an embedded system product development effort:

GBT MP Builds

Putting all those indecipherable acronyms adorning the chart aside, note that the project was performed in 2004 – a mere 3 years after the famous “Agile Manifesto” was hatched. I can’t remember if I knew about (or read) the manifesto at the time, but I do know that Tom Gilb’s “Evo and Barry Boehm’s “Spiral processes had radically changed my worldview of software development. Specifically, the (now-obvious) concept of incremental development and delivery rang my bell as the best way to mitigate risk on challenging, software-intensive, projects.

As the chart illustrates, the actual hand-off of each of the seven builds (to the system integration test team) was pretty much dead nuts right on target. Despite the fact that the project front end (requirements definition and software design) was managed as a “waterfall” endeavor, the targets were met. Thus, I’m led to believe the following trivial trivia:

Not all agile projects succeed and not all waterfall projects fail.